Reconstruction courtyard of paper recycler

Kok Infra B.V. has been asked for the reconstruction of the courtyard of a paper recycler, the entire courtyard of the factory was reconstructed during the long Ascension weekend.

This concerned the execution of the following activities:

  • Taking up and removing approximately 1,000 m2 of existing element and concrete slabs of paving;
  • Repairing and re-profiling the foundation structure;
  • Adjusting the drainage by placing concrete gutters;
  • Sewerage work;
  • The re-laying of 1,000 m2 of concrete slabs paving.

The workactivities were completed quickly and successfully, thanks to the pleasant cooperation with the client.