Update business premises Vaandel

At the end of April, Hoogendijk Bouw will deliver the first building on the Vaandel. It concerns building A, which will be furnished with furniture and other furnishings in the first week of May. From the second week, the building on the Delta will be fully used by Anton Rail & Infra. In the meantime, a lot of work is also being done on the outdoor paving around the building.

The delivery of building B is scheduled for a month later, it will be taken into use by Harder Constructie- & Adviesbureau. Building C will then be completed 2 months later and will be taken into use by De Leeuw Protection Systems.