Alkmaar Central Train Station

In early 2015, the railway station Alkmaar Central placed traverse across the railway tracks. Anton Construction & Concrete Engineering only had 51 hours to get this done successfully. To start the project the columns were cast with a very quick-setting mortar (36N /mm2 in just sixteen hours). As a result it was possible to pour the 700m2 steel concrete floor on Sunday evening. Client was Strukton.