Anton Bouw & Betontechniek was asked to engineer a concrete pit in an existing hall to use the current paper processing lines more efficiently. A conveyor belt in the concrete pit will transport extra material to the press. The challenge of this project was not to disturb the current production process. In addition, we had a very short preparation and execution time, but the project was delivered satisfactorily.

Anton Bouw & Betontechniek

Client

-

Realisation
Anton Bouw & Betontechniek

Start project
November 12th 2018

Project length
4 weeks