Concrete construction for parking garage P3 Schiphol

Schiphol is expanding so the parking need has to be adjusted accordingly. Together with our supply chain partners, we have constructed the concrete construction to the ground floor level of the parking garage P3. And that in just 9 weeks. The scope of the work in broad lines:

210 bases
100 m1 foundation
30 m2 basement
120 m2 floor
600 m3 concrete

The existing parking garage P3 has been upgraded, we have made the supports for the awning.