Constructions for Approach Ring South Groningen

Anton Constructiewerken has delivered two structures that serve as a temporary cable bridge for the constructions of Approach Ring South in Groningen. The client will hang cable packages under the three steel cables.

Constructions for Approach Ring South Groningen

The activities include the production and delivery of the construction and steel cable parts according to the specification of the principal constructor of the client. In collaboration with the company Trans Welding, the assembly was carefully planned, so that during a train-free period, they could carry out all work on location in Groningen in two nights, together with Anton Constructiewerken.

The work is part of building the foundation of the new part of the viaduct over the Europaweg. The activities include driving in tubular piles and vibrating sheet pile planks (partly at night) and supply and removal of building materials and equipment (at night).