During working days in weeks 14 through 46, the porphyry paths will be lifted on part of emplacement Leidschendam and part re-installed.
The following work has been carried out:
- Lifting the trail, also serving as an entry and exit service for train staff
- Construction of porphyry path
- Observe obstacles as required by appointment
- The provision of a route including two overpasses and four scary gates
- Raising various washing and filling hydrants at different locations
- The application of hardening between traces
- Add ballast between road and rail
- Other small work
- Incorporation of cable and gas cookers
The work is carried out in accordance with the CROW 132 ” work in or with contaminated soil ”. The workers in the picture are not working in a contaminated area.