Dismantling platform roofs Groningen station

Anton Rail & Infra have been dismantling the platform roofs of Groningen station on behalf of ProRail. This concerns sub-area B where a total of 31 fields have been dismantled, which together have a total length of approximately 290 metres.

The request for the dismantling of the platform roofs of Groningen station was received a few months before the implementation. And after 6 weeks of preparation time, the platform roofs were dismantled in collaboration with Anton Industrial Service. Because time was of the essence, dismantling was carried out continuously for 7 days, 24 hours a day.

Anton Rail & Infra and ProRail look back on a very successful project.