Anton Construction replaces 24 meters of rails for Europe’s largest steel producer

10 November 2020

For one of the largest steel producers in Europe, Anton Construction replaced approximately 24 meters of running rails of a mobile conveyor belt construction. Extensive steel structural repairs were also carried out and the adjacent floor parts, scraper floors and fences were replaced.

Sinter factory on silent

A downtime of 120 hours was required to carry out the work. In this timeframe, in which the entire sinter plant was at a standstill, shifts were used to ultimately deliver the work to the full satisfaction of the client. Herein, the entire project management, from assignment to completion (including budget control and subcontractor management), was taken over from the client.

Floor renovation conveyor belt construction

As part of the renovation of the conveyor belt construction, the checker plate floor of approximately 50 m2 had to be replaced. In addition to replacing the floors, the entire tension loop and stair tower was also renovated.