Kok Infra B.V. has been asked for the reconstruction of the courtyard of a paper recycler, the entire courtyard of the factory was reconstructed during the long Ascension weekend.
This concerned the execution of the following activities:
- Taking up and removing approximately 1,000 m2 of existing element and concrete slabs of paving;
- Repairing and re-profiling the foundation structure;
- Adjusting the drainage by placing concrete gutters;
- Sewerage work;
- The re-laying of 1,000 m2 of concrete slabs paving.
The workactivities were completed quickly and successfully, thanks to the pleasant cooperation with the client.